A real world project management exercise: turning a client brief that was only a single line ("organize a Women's Day celebration for 30 VIP clients") into a full project charter and a Gantt chart mapped out day by day, complete with dependencies and budget, ready to execute.

PREPARED BY
Alfian Nur Rachman
FOCUS
Project Charter & Gantt Chart Planning
TOOLS USED
Microsoft Word · Excel · Scheduling Built on Formulas
SERVICES

What I Handle in This Area

Two connected PM skills (defining a project properly, then running it in detail) covering the full range of what a project actually needs to stay on track.

📋

Project Charter & Planning

  • Project Planning & Initiation: turning a brief that was only a single line into a clear objective, a defined scope, and a stakeholder map
  • Budget Management: an itemized budget with a contingency buffer, tracked against the schedule
  • Quality Assurance: checking every date and dollar amount between the charter and the schedule before delivery
📊

Scheduling & Execution

  • Task Management: breaking milestones into tasks at the day level, each with an owner, a duration, and dependencies
  • Communication Management: a specific outreach cadence per stakeholder group: vendor briefs, WhatsApp RSVP follow ups, status updates
  • Project Documentation: the charter and schedule kept as one linked set driven by formulas, not static files that quietly drift out of sync
A

Project Charter

Scenario: a realtor (Claire Tan, my Market and Competitor Research client) asked me to organize a Women's Day celebration for 30 VIP clients in Jakarta, with 2 months to plan. Here is how I scoped it.

GUESTS
30

VIP female clients, half day brunch in Jakarta

TIMELINE
8 weeks

August 18 to October 21, 2026, planning through closeout

BUDGET
$3,500

Fully itemized across 6 cost categories

RISKS TRACKED
4

Each with a specific mitigation plan

Project Charter document showing Objective, Scope, and Project Information sections
Project Charter · Section 1Objective, scope, and project information, filled out from the client's brief, which was only a single line
OBJECTIVE

Deepen loyalty, not just host a party

The charter frames the event around strengthening Claire's relationships with her VIP clients and reinforcing brand loyalty, not just logistics for logistics' sake.

SCOPE

A clear line between what is in scope and what is out of scope

Venue, catering, invitations, a guest speaker, activities, and gift bags are in scope. Guest transport, overnight stays, and programming across multiple days are explicitly out of scope; this event runs for a single half day.

RISK EXAMPLE

Low RSVP or late confirmations

Mitigation: send invitations 6 weeks ahead, then follow up personally over WhatsApp at the 2 week and 3 day marks, not just a single invite and hope.

BUDGET EXAMPLE

$150 contingency held back

Catering, gifting, and decor are the categories most likely to run over, so a contingency reserve is locked into the budget from the start, not added after the fact.

📄

Want to see the full project charter?

All 7 sections (objective, scope, deliverables, timeline, risks, budget, team, and stakeholders) exactly as delivered to the client.

View Full Charter ↗
B

Gantt Chart & Timeline

19 tasks across 6 milestones, each with an owner, a duration, and a dependency, not just a list of things to do, but the order they have to happen in.

TASKS & MILESTONES
19 / 6

From "confirm event concept" to "vendor payments and wrap up report," spanning August 18 to October 21, 2026.

DEPENDENCIES TRACKED
100%

Every task states what it waits on (for example "After 1,4"), not a sequential guess, so the schedule holds up if a task slips.

Gantt chart task breakdown table showing all 19 tasks across 6 milestones with owners and dates
Full Task & Milestone BreakdownAll 19 tasks across 6 milestones, each with an owner and dates
Visual Gantt bar chart showing task durations across weeks with dependency labels
Visual TimelineBars set at the day level, generated from live duration formulas, not manually drawn
DEPENDENCY IN ACTION

Why RSVP tracking runs 21 days before headcount is locked

Invitations go out on September 8 and 9, but final headcount is not confirmed until October 12 and 13, a full 21 day window for tracking RSVPs in between, so gift bag and catering numbers (locked in Milestone 4) are based on real confirmations, not guesses.

📊

Want to see the full Gantt chart & budget?

All 19 tasks with owners, durations, dependencies, and the visual timeline laid out day by day, plus the full income and expense budget sheet, linked by formulas throughout.

View Full Gantt Chart ↗
TOOLS USED IN THIS WORK SAMPLE
WMicrosoft Word
EMicrosoft Excel
BBudgeting Built on Formulas
GGantt Scheduling
RRisk Planning